Moved storm pipe beneath Lester Street and had a concrete pour to open the road back up.


Re grading the ditch lines. Looking north.


Looking south at Lester Street.


Looking north from the first drive south of Lester Street.


Looking South toward the end of our drainage ditch.


Tuesday, April 27, 2021

Miller Road - 4/27/2021



Ditch line being regraded and a couple storm pipes have been moved.






Utility locate done and power poles being relocated on the south end.




View of the yard where we are keeping things stored.



2 Excavators, loader, skid steer, roller, dump truck

5 men. Typically 6 but 1 is out sick.

3:00 - 5:00

Friday, April 2, 2021

Miller Road - 4/2/2021



Split up into two crews today. This one is working to the North from Casey’s.


This crew continues our work to the South from the Knight Street intersection.


Edge of the road is taken out and the new ditch line is cut in. They then lay the base rock and compact next to the existing asphalt.


Ditch line near the Knight Street intersection looking to the south.


Ditch line near Casey’s looking to the South.


Ditch line near Casey’s looking to the North.



Thursday, April 1, 2021

Miller Road - 4/1/2021



Continuing to dig out the east side of Miller Road and cut in the new ditch line. At the Knight Street intersection.


Dealing with some valve risers that are connected to our new water main that was installed late last year.


A view of the work looking south down Miller.


A view of the work looking north up Miller.