Tuesday, May 11, 2021

Miller Road - 5/11/2021



Getting the storm pipe in on the south half of the supermarket driveway.


Had to break rock to get depth.


Grading the edge of the road.


Checking for correct depth on new pipe.


Backfilling with rock to allow access.




Getting the north half of pipe lowered to match the south.



Monday, May 10, 2021

Miller Road - 5/10/2021



Southern half of the supermarket driveway has been tore out.


View from the north looking south. New ditch line.


Old storm pipe that was not in use tore out. Plan to install our new pipe tomorrow as well as the flared end.



Friday, May 7, 2021

Miller Road - 5/7/2021



Current state of the supermarket driveway.


Rock delivered.


Remaining storm pipe left to be installed beneath the driveway.


Grading the new ditch line. 


A view of the cut thats been done to the driveway.





Thursday, May 6, 2021

Miller Road - 5/6/2021



Continuing work at the supermarket driveway.


Flared end is installed. As well as half the pipe.


Starting to work on grading the new ditch.


Job board checked out good.







Wednesday, May 5, 2021

Miller Road - 5/5/2021



Getting the residential drive ready for concrete after moving the storm pipe.


Getting forms set up.




Pour complete.


Smoothing out the surface.



Monday, May 3, 2021

Miller Road - 5/3/2021



Moved the storm pipe beneath this residential driveway to match the new ditch line.




Getting rip rap installed on downstream side of new storm pipes.


View of ditch line from Knight Street looking North.


Sunday, May 2, 2021

Miller Road - 5/1/2021



Current state of the lot being used to store equipment.


Grading the ditch line.


Had to stop the crew from installing the two storm pipes in front of these power poles. Per engineer and project manager.


Half day. 3 employees.