3811 Miller Road Improvements
Thursday, October 1, 2020
Miller Road - 10/1/2020
Digging out ditch line in driveway on Miller Road.
Lowering in the flared end section of storm pipe.
Connecting the storm pipe sections in the ditch line. Once sections are connected will backfill with gravel to complete the installation.
Miller Road - 9/30/2020
Getting chlorine/water mixture set up.
Pumping in the chlorine into the new main.
Flushing at the other end and testing our chlorine levels. Once we got what we needed, we shut it down and will let it sit overnight.
Installed a small section of storm pipe.
Friday, September 25, 2020
Miller Road Improvements, 9-25-2020
Arrived on site at 11:20 am.
Installed waterline along south side of Walnut Lane.
Departed site at 11:50 am.
Miller Road Improvements, 9-24-2020
Arrived on site at 9:45 am.
Installed waterline across Walnut Lane and began installing along south side of Walnut Lane.
Departed site at 10:03 am.
Wednesday, September 23, 2020
Miller Road Improvements, 9-23-2020
Arrived on site at 1:26 pm.
Installed waterline between south entrance to Casey’s convenience store and Walnut Lane.
Departed site at 1:40 pm.
Tuesday, September 22, 2020
Miller Road Improvements, 9-22-2020
Arrived on site at 1:35 pm.
Installed waterline across south entrance to Casey’s convenience store.
Departed site at 1:50 pm.
Monday, September 21, 2020
Miller Road Improvements, 9-21-2020
Arrived on site at 10:11 am.
Installed waterline between entrances to Casey’s convenience store.
Departed site at 10:25 am.